Short answer: put the SER through a listed cord grip sized to the jacket's wide axis — 1.1-1.25 in [28-32 mm] on 2/0-2/0-2/0-1 — and bridge the jacket's ridges with neutral-cure RTV where the seal rings land. Or pull the cable through 2 in Schedule 40 PVC and land the conduit on a gasketed hub; the conduit doubles as physical protection. Duct seal belongs behind one of those seals as a second line against drafts, and out of the job as the seal itself. The numbers below follow a 100 A barn feed on 2/0 aluminum; measure your own cable before anything goes on an order.
Measure the jacket, then pick the route
SER is round in name only. The jacket is extruded over the conductors laid side by side, so it comes off the reel with lengthwise ridges and clefts instead of a smooth cylinder, and a round seal ring rides on the ridges.
Build the number first. One large US wiremaker's 2/0-2/0-2/0-1 SER datasheet lists each 2/0 conductor at 0.376 in over 12 strands, and that is where the geometry starts. Two conductors side by side span 0.752 in. The third nested on top pushes the wide axis to 0.376 + 2 × (0.376 × 0.866) ≈ 1.03 in before insulation and jacket; finished cable lands between 1.1 in and 1.25 in [28-32 mm]. Set your calipers on the widest point and the narrow one, and order to the wide number, because that is the axis the grip has to close on.
Then read the print on the jacket. A sunlight-resistant marking means the jacket can face the weather. When it is missing, the cable belongs in conduit and Route B is your route.
Route A: a cord grip on a round cutout
A cord grip closes a round sealing insert on the cable, so the fitting carries the water duty and the RTV makes the non-round jacket behave. Spend a minute on what a cord grip means on a US spec before you order.
- Pick the grip on its clamping range. The range printed in the datasheet must bracket your caliper number — 1.18 in [30 mm] in this example. At 1.1-1.25 in you are usually into a 1¼ in NPT or a metric M50 body. A nylon body on a stainless box skips a dissimilar-metal pair and still seals; the sealing lives in the insert and its gaskets.
- Cut the hole to the fitting, not to the cable. Punch or holesaw, then deburr the wall flat so the grip's gasket seats without a gap. The trade sizes come from UL 50's Table 71-1A, the knockout-and-fitting-dimension table; sizes below are nominal and the grip's datasheet governs:
| Fitting trade size | Hole in the box | Typical duty |
|---|---|---|
| 1 in NPT | 1 3/8 in [35 mm] | smaller SE cable, about 0.6-1.0 in |
| 1¼ in NPT | 1 3/4 in [44 mm] | 2/0 SER at 1.1-1.25 in |
| 1½ in NPT | 2 in [50 mm] | 3/0 to 4/0 SER |
| 2 in | 2 1/2 in [64 mm] | Route B conduit and hub |
The cutouts and glands guide covers edge spacing when you lay out the face. 3. Clean the jacket. Isopropyl alcohol and a dry cloth where the insert will sit; sealant sticks poorly to reel grime. 4. Fill the ridges. Neutral-cure RTV worked into the clefts, plus a thin film on the insert's sealing rings. Neutral cure matters here — it releases nothing that attacks metal parts in the box. 5. Assemble and tighten. Grip gasket between body and enclosure wall, locknut snug inside, then the gland nut until the cable will not turn or slide by hand. 6. Place the entry low. Bottom or a side face. A top entry is a hub-versus-sealing-locknut job rather than a plain grip, and it wants a drip loop in the cable.
Route B: the SER inside sealed PVC conduit
Conduit wins when the run faces damage or sun the jacket is not marked for, and it turns the entry into a threaded hub — the easiest joint to keep dry on a box wall. PVC landing on a threaded hub covers that joint in detail.
Size the conduit on the fill rules, which allow a single cable 53 % of the conduit's internal area. For the 1.18 in example cable:
- Cable area: π × (1.18 / 2)² = π × 0.348 = 1.09 in²
- 2 in Schedule 40 PVC: about 3.2 in² internal, so 53 % allows 1.70 in² — fits with margin
- 1½ in Schedule 40 PVC: about 2.0 in² internal, so 53 % allows 1.06 in² — under the cable, and the pull would chafe besides
Two-inch it is, then:
- Glue every joint with primer and solvent cement. Above ground, add an expansion fitting: PVC moves about 4 in [100 mm] per 100 ft [30 m] over a 100 °F swing.
- Pull with long-radius bends and cable lubricant. Anything past a couple of 90s earns a pull box on the run.
- Land the conduit on a gasketed hub, thread sealant on the PVC adapter, gasket between hub and box.
- Stop the chimney. A duct-seal plug inside the hub, on the dry side of the gasket, halts the slow airflow that carries moist air through conduit and drips it out at the low point.
What duct seal is actually for
The putty is a plugging compound for drafts, dust and insects, and its own label keeps it indoors: heat slumps it and standing water loosens its grip on a wet surface. Outdoors it serves as the second line, packed on the dry side of a grip or hub, and as the plug in a conduit mouth. The primary seal stays mechanical. When the putty goes grey and crumbly, press in fresh — five minutes of maintenance instead of a rebuilt entry.
Grounds, bonding and the splice
In 4-conductor SER the bare #1 is your equipment grounding conductor. Land it on the box's ground bar, splice the neutral straight through on insulated connectors, and keep it off the metal: NEC 250.6 puts neutral current off the enclosure by landing neutrals on an isolated terminal and grounds on the ground bus. The grip, hub and stainless walls together form the bonding path NEC 250.96(A) describes — metal parts joined so they carry a fault. NEC 250.12 makes the same point for paint: it comes off the threads and contact surfaces at those connections. Boxes we build are cut from bare stainless, so the grip seats on metal. Splice 2/0 aluminum in listed aluminum-rated connectors with antioxidant, torqued to the value printed on the connector. Grounding and bonding across the panel shows where each conductor lands.
One habit before the box opens: kill the feeder at its breaker, lock it out, and verify absence of voltage. A 100 A feeder deserves the same treatment as the service.
Prove the entry holds
Give the RTV a full day to cure, then test with water before the box goes on the wall. Three minutes of garden hose on the entry from about 1 ft [0.3 m], swept across the fitting, is a fair field check; the laboratory version of the same idea is the IEC 60529 jet test for second digit 6 — a 12.5 mm nozzle at 100 L/min for 3 min. Open the box after the first real weather and look at the lowest corner and the splice lugs. Sealing the connectors themselves matters as much as the entry, because a perfect grip over a wet splice still corrodes aluminum.
The stainless boxes we build are rated NEMA 4X / IP66 by the manufacturer and not UL listed, and the finished box is rated by its weakest part — which on a field-wired entry is usually the fitting you just installed.
Which route, and what to order
Decision first. A short rise out of a wall with a bottom entry: grip on a round cutout. An exposed run, physical damage, or a jacket with no sunlight marking: 2 in PVC on a gasketed hub. Cold climates with wide temperature swings lean toward the grip — one fewer glued joint to breathe.
On the order:
- The box, from the stainless junction-box line, deep enough to leave about 2 in [50 mm] clear around the finished splices. Near salt water, take the 316L side of the outdoor enclosure range.
- The cutouts, placed before the box is built with the cutout designer: the 1 3/4 in [44 mm] grip hole on a side face, hub holes where the conduit lands. Custom work is delivered in 10 business days from your approval of the drawing.
- The grip, 1¼ in NPT or M50, clamping range covering your caliper number, plus a spare sealing insert.
- The RTV, neutral cure, one small tube.
- For Route B, the gasketed hub in the conduit's trade size, the expansion fitting, and a tub of duct seal for the plug.
Catalog dimensions to compare
Compare these catalog dimensions with your component layout. Open each enclosure for its rating, material and usable space, then check those specifications against your application.
| Enclosure | Material | Outside H x W x D / display | Rating |
|---|---|---|---|
| 6 × 6 × 4 in | 304 stainless | 6 x 6 x 4 in | Rated NEMA 4X / IP66 by the manufacturer; not UL listed |
| 8 × 6 × 4 in | 304 stainless | 8 x 6 x 4 in | Rated NEMA 4X / IP66 by the manufacturer; not UL listed |
| 10 × 8 × 4 in | 304 stainless | 10 x 8 x 4 in | Rated NEMA 4X / IP66 by the manufacturer; not UL listed |
| 12 × 10 × 6 in | 304 stainless | 12 x 10 x 6 in | Rated NEMA 4X / IP66 by the manufacturer; not UL listed |
Questions
Do the oval SE cable connectors work on SER cable?
No. Those fittings clamp the flat, style-U SE cable profile. SER's jacket is round with lengthwise ridges and runs about 1.1-1.25 in [28-32 mm] on 2/0-2/0-2/0-1, so use a round cord grip a trade size up, with neutral-cure RTV worked into the ridges where the insert bears.
Does the conduit entry need a drain at the low point?
A drain belongs on a Type 3R box, where NEC 314.15 permits openings of 3 mm (1/8 in) to 6 mm (1/4 in) in boxes and conduit bodies listed for damp or wet locations. On a sealed 4X box, keep the holes plugged and stop the water at the conduit instead — the duct-seal plug inside the hub keeps moist air from moving.
How long does the RTV fillet need before the hose test?
About an hour to skin at room temperature and about 24 h to full cure for a fillet a few millimetres thick. Hose-test the day after assembly and look again after the first heavy rain; silicone that has not cured through smears at the rings instead of sealing.
Can a metal grip go on a plastic junction box?
Yes, with one wiring change. A nonmetallic box gives a metal fitting no ground path of its own, so NEC 314.3 allows it only with the metal parts bonded together inside the box — run the equipment grounding conductor to a bonding lug on the grip or hub.