Direct burial junction box: splice box, connectors and fill

Pull one continuous 6 AWG length if it reaches, because a run with no splice has nothing to flood. When it does not, set a 9 x 15 x 9 in open-bottom handhole on gravel, fill the bottom third to half with washed stone, and make each splice with connectors listed for wet locations and rated for direct burial and submersion. A sealed box buried in a mulch bed holds water against the splices; the open bottom drains it.

NEMA4 Enclosure engineering team · Published November 14, 2026 · 7 min read

Short answer: pull one continuous 6 AWG length if it reaches, because a run with no splice has nothing to flood. When it does not reach, set an open-bottom handhole — a 9 x 15 x 9 in polymer box or a 10 in round concrete one — on gravel. Fill the bottom third to half with washed stone, and make every splice with connectors listed for wet locations and rated for direct burial and submersion. Traffic-signal crews splice in the ground exactly this way. The box takes water and drains it, and the connectors are the part that stays rated.

Why the ground is a wet location

Everything you bury sits in a wet location, by rule and by physics. The soil holds water after every rain and pushes it at every seal, day and night, in a mulch bed as much as in a swamp. Run the pressure arithmetic once: 6 in [150 mm] of standing groundwater is 0.22 psi [1.5 kPa], which puts about 30 lbf [140 N] on a 1 ft² [0.09 m²] enclosure face. That load holds constant, month after month, so the gasket creeps, the box floods, and a sealed box cannot drain. The water then sits on your splices until someone opens the lid. What flooded conductors are still good for after that is its own question, covered in flooded pull box conductors.

Our stainless wall-mount boxes are rated NEMA 4X / IP66 by the manufacturer; not UL listed. That rating is earned with dust and hose-jet tests, as the NEMA 4X versus IP66 guide lays out, and it says nothing about holding back a water table. In the ground, the open-bottom handhole wins by refusing the fight: water enters, passes through washed gravel, and leaves.

Straight-through, handhole or sealed box

Decide in this order, and the first row is always the cheapest:

Approach Use it when What it costs you
One continuous length, no box The pull reaches end to end Nothing; always the first choice
Open-bottom handhole with listed wet-location splices The run needs a buried splice or pull point A lid in the garden you have to find again
Sealed enclosure, buried The equipment inside must stay dry at all times A custom pressure-and-drainage design, and a repair when it leaks

A straight-through pull gives you the splice you never maintain. Where the run must break, the handhole is the standard answer, from irrigation valves to traffic signals. A gate feeder built the same way is walked through in buried handhole splices for a gate feeder. Keep the sealed-buried route for electronics that must stay dry, and treat it as a custom design review where you bring depth, duration and fluid, through the contact page. When submersion is permanent, potting the splice in epoxy is the competing method, compared in potting epoxy versus a rated enclosure. If a closed box ends up underground anyway, sealing a buried junction box against leaks covers the gasket and entry work.

The connectors carry the rating

Underground, the connectors do the sealing work the enclosure does above grade. Two families are listed for it:

  • Silicone-gel-filled twist-on connectors, in the size printed for two of the power conductors — one per splice.
  • Insulated set-screw blocks, one screw each end, marked and listed for direct burial and submersion.

Match the printed conductor range to the exact pairing you are making: the two power conductors at each hot splice, and (2) 10 AWG for the ground. Within one maker's connector line, only part of the range usually carries the submersion rating, so the marking on the bag and on the body decides it. Torque set-screws to the inch-pound value moulded on the connector, with a wrench that reads inch-pounds. Taping a dry-location wire nut adds no wet-location listing; the listing travels with the connector itself, and the tape stays out of the argument.

The box, the lid and the gravel

For two power splices and one ground splice, a 9 x 15 x 9 in polymer handhole or a 10 in round box in concrete or plastic gives room for staggered connectors and two hands. This splice sits one size below the 4 AWG threshold where the NEC pull-box multipliers start — 8 times the conduit diameter on a straight pull — so pull box sizing for 4 AWG and larger governs the bigger feeders, and here you size for access.

Polymer is light and shrugs off corrosion; concrete shrugs off shovels and settling. The lid follows traffic: pedestrian-rated under mulch, traffic-rated where a wheel can cross. Set the box on 4 in [100 mm] of tamped gravel for drainage, with the rim flush with grade so the lid sheds water and leaves no edge to catch a foot. Put it where the ground actually drains — a low spot that ponds turns a handhole into a cistern. Fill the bottom third to half of the inside with washed gravel, 3 to 4.5 in [75 to 115 mm], so the splices stand above whatever water collects.

Before any trenching, have the underground utilities marked through your area's one-call locate service. One call, one short wait, and the trench is the safe kind of surprise-free.

Cover depth and conductor insulation

The NEC's general cover for 0-600 V runs is 24 in [600 mm] over direct-buried cable and 18 in [450 mm] over nonmetallic conduit. Rigid metal conduit buys the shallowest trench at 6 in [150 mm]. Rows under driveways and streets differ, so match the trench to the surface it crosses and the edition your inspector enforces. Conduits enter the handhole low on the wall and sweep to full cover a short distance out.

Insulation carries the same wet-location logic: underground, the conductor is THWN-2 or XHHW-2. Most THHN on today's reels is dual-rated and printed THHN/THWN-2 on the jacket, so read that print before the pull. Plain THHN keeps its rating only where it stays dry, and below grade stays wet.

A 240 V feeder splice in the handhole

Inputs, with where each comes from: a 240 V single-phase run to a 48 A EV charger, the example load; a 60 A breaker ahead of it; two 6 AWG copper THHN/THWN-2 conductors and one 10 AWG copper equipment grounding conductor. NEC Table 250.122 sizes that grounding conductor from the breaker rating — 60 A means 10 AWG copper. The handhole is a 9 x 15 x 9 in polymer box in a mulch bed, with conduits entering low on the end wall.

The rules in words: EV charging is a continuous load, so the conductors carry 125 % of it. The NEC's 75 C ampacity table for copper conductors rates 6 AWG at 65 A in that column. Gravel fills the bottom third to half, and the splices stagger so connectors stay unstacked.

The arithmetic:

  • Required ampacity: 48 A × 1.25 = 60 A. The power conductors at 75 C carry 65 A, so they fit with 5 A spare.
  • Ground check: 60 A device → 10 AWG copper EGC, spliced with its own listed connector in the (2) 10 AWG range.
  • Gravel: 9 in × 1/3 to 1/2 = 3 to 4.5 in of stone, leaving 4.5 to 6 in of clearance; a typical 6 AWG insulated connector runs about 3 in [75 mm], so it clears.
  • Layout: L1, L2 and the ground at 4, 8 and 12 in along the 15 in [380 mm] wall.
  • Cover: 18 in [450 mm] of cover over the conduit before backfill.

The decision, with its threshold: every conductor joint below grade is made only with connectors listed for wet locations and rated for direct burial and submersion; anything else goes above grade. Photograph the finished splices and measure to two fixed points before backfill — a box you can find again is an outage you can clear.

What to specify

Item For this job
Handhole 9 x 15 x 9 in polymer, or 10 in round concrete; pedestrian lid in a mulch bed
Drainage 4 in gravel bed under the box; washed gravel filling the bottom third to half inside
Power splices 2 connectors, wet-location listed, direct-burial and submersion rated, range covering (2) 6 AWG
Ground splice 1 connector, same listing, range covering (2) 10 AWG
Conductors 6 AWG copper THHN/THWN-2, jacket print checked; 10 AWG copper EGC
Cover 18 in over nonmetallic conduit, 24 in where the cable is direct-buried
Records Photo of the splices and dimensions from two fixed points, before backfill

The other way to keep the rating is to lift the splice out of the ground: a gasketed stainless box on a post beside the bed — stainless junction boxes — keeps the joint inspectable, and the outdoor enclosures guide covers sun, rain and temperature for everything above grade. We cut those boxes to your gland and connector layout and deliver in 10 business days, custom work counted from your approval of the drawing. Below grade the logic stays: 18 in of cover, wet-location insulation, and splices rated for the water they will meet.

Catalog dimensions to compare

Compare these catalog dimensions with your component layout. Open each enclosure for its rating, material and usable space, then check those specifications against your application.

EnclosureMaterialOutside H x W x D / displayRating
6 × 6 × 4 in304 stainless6 x 6 x 4 inRated NEMA 4X / IP66 by the manufacturer; not UL listed
8 × 6 × 4 in304 stainless8 x 6 x 4 inRated NEMA 4X / IP66 by the manufacturer; not UL listed
10 × 8 × 4 in304 stainless10 x 8 x 4 inRated NEMA 4X / IP66 by the manufacturer; not UL listed

Questions

Can I bury a sealed NEMA 4X enclosure instead of a handhole?

Keep it above grade. Type 4X is a hose-jet rating, and our wall-mount boxes are rated NEMA 4X / IP66 by the manufacturer and not UL listed, with no burial or immersion rating. Six inches of standing groundwater puts about 30 lbf on a one-square-foot face for months, gaskets creep, and a flooded sealed box cannot drain. Equipment that must stay dry underground is a custom design review: bring depth, duration and fluid.

Are wire nuts allowed in a buried splice box?

Only the ones listed for it. A silicone-gel-filled twist-on connector in the range printed for two of your power conductors, or an insulated set-screw block rated for direct burial and submersion, holds the wet-location listing. A dry-location connector wrapped in tape keeps no listing underground; taping adds nothing. Match the printed conductor range to your splice, and torque set-screws to the value marked on the connector body.

How deep do the box and the conduits go?

The rim sits flush with grade so the lid drains and leaves no trip edge. In the general 0-600 V case the NEC calls for 24 in of cover over direct-buried cable and 18 in over nonmetallic conduit, and rigid metal buys 6 in. The conduit entries sit near the bottom of the handhole; sweep to full cover just outside the box.

What size handhole for a 240 V, 6 AWG splice?

A 9 x 15 x 9 in polymer box or a 10 in round concrete one gives room for three staggered splices and two hands. Because this wire is smaller than 4 AWG, the NEC pull-box multipliers (8 times the conduit diameter for a straight pull) start above your wire size, so you size the box for access. Going one size larger costs little in a hole you dig once.

Is THHN insulation allowed underground?

Underground counts as a wet location, so the insulation must be THWN-2 or XHHW-2. Most THHN sold today is dual-rated and printed THHN/THWN-2 on the jacket, so read the print before you pull. The 10 AWG equipment grounding conductor splices in the same box with its own connector from the same listed family.

Checklist before you order

Specify it once, built to your drawing

  • Environment and NEMA type: Type 1, Type 3R, Type 4, Type 4X, Type 6P, Type 12, Type 13 (manufacturer ratings, not UL listed)
  • Material: 304 stainless steel, 316L stainless steel, Powder-coated carbon steel, Aluminum, Polycarbonate, Fiberglass (FRP)
  • Size: inside or outside height, width and depth, with the depth your deepest component needs
  • Cutouts, glands and windows, dimensioned from one datum on each face
  • Mounting and access: wall, pole or stand, hinge side, mounting panel
  • Quantity: from one piece

Delivered in 10 business days, anywhere in the world. Counted from your order; for custom work, from your approval of the drawing.

Start a junction box from 6 × 6 × 4 inRequest a custom quote

Stainless junction boxes: sizes for this job