NEMA 250 and the NEC leave the penetration count to the enclosure maker; the wall sets the working limit. Space gland centers two boss diameters apart, keep the hole-to-bend margin clear of bends and the gasket path, and a 16 x 8 in bottom wall takes five 1 in glands while losing about 5% of its sheet.

NEMA4 Enclosure engineering team · Published November 9, 2026 · 7 min read

Short answer: no standard caps the count. NEMA 250 and the NEC print no maximum number of penetrations, so the wall itself sets the limit, and these numbers keep it honest. Space hole centers at least two gland-boss diameters apart — 3 in [76 mm] for a typical 1.5 in [38 mm] boss — and keep every hole clear of bends, corners and the gasket path by the edge margin in the table below. On the 16 x 8 in bottom wall of a 20 x 16 x 8 in box, that gives you five 1 in glands in a single row. The row removes about 5% of the sheet. Spaced that way, the wall stays flat and the door still closes. Crammed shoulder to shoulder, the same five holes can bow the flange enough to open a gasket gap.

What actually limits the count

ANSI/NEMA 250-2020 covers enclosure construction, design tests, marking and field modifications. It names neither a maximum hole count nor a percentage of wall area. The NEC is silent on hole count too: it sizes boxes by the conductor volume inside and by bending space at the terminals. NEC 312.6 sets that space by wire size: 2.5 in for 2 AWG with one wire per terminal. Count conductors rather than holes, because a dozen glands bring a dozen bending-space demands faster than the sheet complains.

The percentage many people half-remember belongs to conductors, not metal. Wiring-duct fill tables top out at 50% of the duct interior, citing NFPA 79-2012 section 13.5.2, because round cables leave air gaps however you pack them. Those tables govern what passes through the holes. They say nothing about how many holes the wall takes.

Two parties can still cap you. The enclosure maker's documentation may restrict hole positions, and for hazardous-location Types 7 and 9 it always does. Certified entry methods leave little freedom there, and we do not build those boxes. Ratings are the other checkpoint: our boxes are rated NEMA 4X / IP66 by the manufacturer, not UL listed, and in US installations NEC 110.28 keeps the IP code and the enclosure Type rating separate on a specification. The fundamentals behind holes, glands and windows sit in the cutouts, glands and HMI windows guide.

Spacing rules that keep the wall stiff

Treat the table as the shop rule for a light stainless wall. Small stainless boxes commonly use 18 gauge sheet, 0.048 in [1.2 mm] thick, or 14 gauge at 0.075 in [1.9 mm], per the standard sheet-gauge tables.

Dimension Keep at least Why
Center-to-center 2 x boss OD: 3 in [76 mm] for a 1.5 in [38 mm] boss one full boss diameter of solid sheet between holes
Hole to bend or corner 1 in [25 mm] bends and corners carry the wall's stiffness
Hole to door flange and gasket path the same 1 in [25 mm] the flange stays flat for even gasket compression
Hole to hinge and latch bosses the same 1 in [25 mm] the hardware already loads those areas
Web between 1.25 in [32 mm] holes at 3 in centers 1.75 in [44 mm] resists denting and line-hinging along the row

Read the edge margin as one value from this table: 1 in [25 mm] of solid sheet between any hole and every bend, corner, flange, gasket path and hardware boss. Every mention below of "the margin" means that number.

Bigger glands scale the rule directly: a 2 in boss wants 4 in [102 mm] centers. Heavier or ribbed walls tolerate tighter spacing. The worst case is a row of small glands on thin sheet, where closely spaced holes act like a perforated line the wall can hinge along. That is the mechanism behind a door that suddenly will not close.

Worked example: five glands on a 16 x 8 in bottom wall

Take our 20 x 16 x 8 in wall-mount box (outside 20 x 16 x 8 in H x W x D) in 304 stainless or the identical geometry in 316L for chloride washdown. The bottom wall measures 16 x 8 in [406 x 203 mm].

  • Margin: the 1 in [25 mm] band all round, so the first hole center sits at 1 + 0.75 = 1.75 in [44 mm] from the edge, because the boss radius is half the 1.5 in OD. The usable center span runs 16 − 2 x 1.75 = 12.5 in [318 mm].
  • Centers: 2 x 1.5 = 3 in [76 mm]. Five holes span 4 x 3 = 12 in [305 mm], inside the 12.5 in span with half an inch to spare.
  • Metal removed: a 1.25 in [32 mm] clearance hole cuts 0.785 x 1.25 x 1.25 = 1.23 sq in each. Five holes take 6.1 sq in from the 16 x 8 = 128 sq in wall — 4.8%, call it 5%. In metric: 804 sq mm x 5 = 4,020 sq mm of an 82,400 sq mm wall.
  • Result: 1.75 in [44 mm] webs of solid sheet between holes, corners and flange untouched, and the 7.88 in [200 mm] inside depth clears the gland tails above the panel.

Double the density and the webs fall to 0.25 in [6 mm]. That is where a thin wall starts to wave.

What you need

  • A cable schedule with every cable's outside diameter. The gland seals on the cable OD, so match the clamp to the cable before you mark a hole.
  • Gland datasheets: boss OD, clearance hole diameter, and the gland's own IP and Type rating.
  • The layout: the cutout designer lays holes on any face, checks spacing, and sends the drawing with your quote request.
  • For field work: a fine-tooth hole saw at low speed, lubrication, and a deburring tool. The cutting how-to walks the cut.
  • Glands rated IP66 / NEMA 4X, with sealing washers and locknuts.

Laying out and cutting the holes

  1. Pick each gland from the cable's OD, then read its boss OD and clearance hole from the datasheet. Metric threads are tabulated in the M20 hole-size article.
  2. Mark the margin band from the table above around every bend, corner, flange edge and gasket path on the chosen wall.
  3. Set centers at twice the boss OD, in one row where the wall allows it. Stagger a second row only on 14 gauge sheet or thicker, and keep the rows two boss diameters apart as well.
  4. Order the holes from the factory where you can. Draw them in the cutout designer and send the layout with your quote; the custom cutouts page sorts new openings in a stock body from a fully custom body. Custom holes are cut on flat sheet before bending, and the box is delivered in 10 business days from your approval of the drawing, anywhere in the world.
  5. For a field cut, pilot each hole, saw at low speed, and deburr both faces.
  6. Fit each gland with its sealing washer inside and locknut outside, tightened to the gland's own instructions. The installation how-to shows what preserves the rating.
  7. Close the door and run the checks below before the box goes on the wall.

Checks when the holes are in

  • The door shuts with hand pressure and no rub; a strip of paper pulls out of the closed gasket with an even, light drag all the way round.
  • Every clamp grips its own cable inside the gland's stated OD range; a cable below the clamp minimum is the first leak in the row.
  • Holes are deburred inside and out. Stainless needs no touch-up coating, unlike painted steel.
  • Outdoor bottom entries carry a drip loop below every gland.
  • Every fitting on that wall is rated to the assembly duty. One unrated vent, drain or connector sets the whole box at that part's level.

Mistakes that cost the rating or the wall

  • Holes through the flange face or gasket path. Keep them inside the margin band; that face is the seal.
  • Centers squeezed under one boss OD. The web falls away, the wall hinges along the row, and the door gap opens at the latch corner.
  • Leftover space filled with an unrated vent or drain. The assembly rating drops to that fitting's level, so pick rated parts.
  • Marking holes after the box is mounted and loaded. Lay out on the drawing first, cut once.
  • Field cuts that drift. A hole saw walking on stainless ruins the web you were saving; factory cuts on flat sheet land where the drawing puts them.

When the holes will not fit

  • Up to five 1 in glands, or six 0.75 in glands at 2.25 in [57 mm] centers (a 1.125 in [29 mm] boss, so twice the OD), fits the 16 x 8 in bottom wall in one row. Build it as drawn.
  • Six to ten entries, or mixed gland sizes: move the entries onto a bolted stainless gland plate. The plate carries the holes off the box wall, drills as densely as the glands need, and swaps out later without touching the enclosure. Gland plate versus a split entry system covers the high-count option.
  • More than that, or a second row on thin sheet: size up. The 20 x 20 x 8 in 304 box widens the bottom wall from 16 to 20 in, which takes the row to six 1 in glands at the same 3 in centers (span 15 in against a 16.5 in usable span). The enclosure sizing guide walks the volume behind the choice.
  • Whatever the count, the rating rides on the glands. Every penetration sealed with a gland rated for the duty keeps the manufacturer's NEMA 4X / IP66 rating.

Catalog dimensions to compare

Compare these catalog dimensions with your component layout. Open each enclosure for its rating, material and usable space, then check those specifications against your application.

EnclosureMaterialOutside H x W x D / displayRating
20 × 16 × 8 in304 stainless20 x 16 x 8 inRated NEMA 4X / IP66 by the manufacturer; not UL listed
20 × 16 × 8 in316L stainless20 x 16 x 8 inRated NEMA 4X / IP66 by the manufacturer; not UL listed
20 × 20 × 8 in304 stainless20 x 20 x 8 inRated NEMA 4X / IP66 by the manufacturer; not UL listed
12 × 10 × 6 in304 stainless12 x 10 x 6 inRated NEMA 4X / IP66 by the manufacturer; not UL listed

Questions

Is there a percentage limit on penetrations, like the 40% fill rule?

Those percentages belong to conductor fill, not to holes. A wiring-duct maker caps its fill tables at 50% of the duct interior, citing NFPA 79-2012 section 13.5.2, because round cables leave air gaps. No enclosure standard prints a percentage of wall area for gland holes. Work to spacing instead: 3 in [76 mm] centers for a 1.5 in [38 mm] gland boss, and the hole-to-bend margin from the table below at every bend and gasket path.

Does a field-drilled hole drop the Type 4X / IP66 rating?

The rating follows the gland and its installation, not who cut the metal. Fit a gland rated for Type 4X / IP66 duty, matched to the cable's outer diameter, with its sealing washer and locknut fitted as the gland's instructions describe, and the assembly keeps the manufacturer's rating; ours are rated by the manufacturer and are not UL listed. Keep the hole inside the same margin from bends either way, because the structural damage is separate from the seal.

How many glands fit on the bottom of a 16 x 8 in wall?

Five 1 in glands at 3 in [76 mm] centers, laid out from a 1.75 in [44 mm] first center, span 12 in of the 12.5 in usable width. Six 0.75 in glands at 2.25 in [57 mm] centers span 11.25 in and fit the same wall. Beyond about eight entries, move to a bolted gland plate or a wider box rather than compressing the spacing.

Do hazardous-location enclosures have a hard penetration limit?

Yes, a real one: Type 7 and Type 9 explosion-hazard enclosures use certified entry methods, so the number and position of openings follow that equipment's certification, and the maker limits them. Those rules do not apply to the ordinary Type 4X boxes in this article, and we do not build Type 7 or 9 enclosures. For a standard washdown or outdoor box, spacing and gland rating are the limits that matter.

Checklist before you order

Specify it once, built to your drawing

  • Environment and NEMA type: Type 1, Type 3R, Type 4, Type 4X, Type 6P, Type 12, Type 13 (manufacturer ratings, not UL listed)
  • Material: 304 stainless steel, 316L stainless steel, Powder-coated carbon steel, Aluminum, Polycarbonate, Fiberglass (FRP)
  • Size: inside or outside height, width and depth, with the depth your deepest component needs
  • Cutouts, glands and windows, dimensioned from one datum on each face
  • Mounting and access: wall, pole or stand, hinge side, mounting panel
  • Quantity: from one piece

Delivered in 10 business days, anywhere in the world. Counted from your order; for custom work, from your approval of the drawing.

Build it from 20 × 16 × 8 inRequest a custom quote

NEMA 4X enclosures: sizes for this job

Keep reading

More on layout and installation

All articles

Buying guides

The guides behind this answer

All guides