Keep remote I/O inside an enclosure unless the complete exposed installation meets the washdown chemistry, spray and electrical requirements. Machine mounted I/O can shorten wiring, but every connector becomes part of the environmental barrier. Four 1.5 A solenoids require 6 A simultaneously, plus checks of channel, group and supply limits.

NEMA4 Enclosure engineering team · Published October 30, 2026 · 6 min read

Keep the protective enclosure unless the complete exposed I/O installation is documented for your washdown chemistry, spray conditions and actuator loads. Moving I/O onto the machine removes a door and shortens field wiring, but exposes every connector and cable seal.

For salty, greasy service, compare complete installations rather than module ratings alone. Four solenoids drawing 1.5 A each also require a separate electrical check. Neither a communication connection nor an ingress rating establishes actuator power capacity.

Compare the complete installations

Decision point Machine mounted I/O Remote I/O inside an enclosure
Water exposure Module, connectors and cables directly face the cleaning environment Enclosure and cable entries form the primary water barrier
Chemical exposure Housing, seals, cordsets, caps and labels all need compatibility Exterior metal, gasket and entry fittings need compatibility; internal equipment stays protected
Solenoid power Check individual outputs, port supplies, groups and total current Output modules or interface devices can be selected separately from the exterior enclosure
Maintenance access Replacement usually avoids opening a cabinet, but exposes connector interfaces Internal access requires opening and correctly resealing the door
Wiring Short local cables can reduce field termination work More wiring enters the enclosure, requiring space and sealed entries
Expansion Limited by available ports, power capacity and mounting positions Limited by backplate space, wiring space, supply capacity and heat
Main vulnerability An unsuitable cordset, loose coupling or missing port cap A damaged gasket, unsuitable entry fitting or unlatched door

An ingress code describes specified tests, not unlimited resistance to cleaning. Confirm the standard behind an IP69 or IP69K claim. IEC 60529 includes IPX9 testing; ISO 20653 uses IPX9K terminology. Neither establishes compatibility with your sanitizer or grease remover.

Our wall-mount enclosures are rated NEMA 4X / IP66 by the manufacturer; not UL listed. Those ratings do not establish suitability for hot, high-pressure cleaning. An exposed module's higher ingress code does not transfer to an enclosure containing it, either.

Where machine mounted I/O wins

Exposed I/O makes sense when suitable mounting positions exist close to the sensors and valves, outside concentrated spray paths. Short cordsets can replace long multicore cable runs and reduce internal terminal wiring.

A sealed module also removes one recurring maintenance task: opening and relatching an enclosure door. It does not remove sealing work. Every replacement cordset introduces another opportunity for contamination, damaged seals or incorrect coupling torque.

Specify the complete connection system, including mating connectors, unused-port caps, power connectors and cable jackets. Connector size and pin count alone do not prove compatibility. Confirm the required mating parts and assembly instructions in the device documentation.

The guidance on sealing connectors inside an outdoor junction box explains why protecting a connection requires more than covering its contacts. With exposed I/O, the connector itself must provide the documented environmental protection.

An open, drainable spray guard can reduce direct impact where the installation instructions permit it. Keep drainage, cleaning access and connector removal clear. A guard does not upgrade a rating or justify selecting equipment below the project's required protection level.

Where enclosed remote I/O wins

An enclosure separates ordinary internal electronics from salt deposits, grease and repeated external cleaning. It also allows the output hardware to be selected independently from the washdown-facing housing.

That separation helps when the required actuator current exceeds the available exposed module's output capacity. Internal remote outputs, protected interface devices or a suitable valve manifold may provide a better architecture. Each still needs documented electrical compatibility.

Choose the exterior material against the actual chemicals. In chloride exposure, 316L generally offers better pitting resistance than 304, but neither is immune to corrosion. Concentration, temperature, contact time and rinsing all affect the result.

The enclosure only works if its entries and door remain sealed. Use compatible fittings, correct cable sealing ranges and documented installation torque. The article on installing a cable gland without losing the rating covers those entry details.

Enclosing the electronics also changes the thermal calculation. Include power-supply losses, output losses and any internal interface coils. Do not count the full electrical power delivered to external solenoids as enclosure heat. Use the enclosure heat calculation guide for the thermal sizing method.

Retain enough space to reach terminals, replace modules and inspect the gasket. A compact installation that requires pulling cables against the door seal is not a maintainable installation.

Decide from the cleaning conditions and electrical loads

Match the cleaning process before choosing the architecture

Write down the cleaner and sanitizer names, working concentrations, temperatures, contact times and rinse procedure. Include salt accumulation between cleanings, not just conditions immediately after rinsing.

Then record spray pressure, water temperature, nozzle distance and direction at the proposed equipment location. Compare those conditions with the complete assembly's documented limitations. A general description such as daily washdown is not enough.

Keep the enclosure when chemical compatibility is uncertain, direct spray cannot be avoided, or internal service flexibility matters most. However, do not retain an inadequately rated enclosure simply because its electronics remain inside it. Change the location, cleaning arrangement or enclosure specification to meet the actual exposure.

Choose exposed I/O when the complete module-and-cordset system has documented compatibility and accessible, protected mounting positions. A split arrangement can also work: exposed sensor interfaces near the process, with higher-current switching inside an enclosure.

For either arrangement, make inspection possible without dismantling unrelated equipment. The outdoor sensor enclosure maintenance article covers practical checks for seals, entries and mounting condition.

Check four 1.5 A solenoids at every electrical limit

Assume four external 24 VDC solenoids, each drawing 1.5 A continuously when energized. Their simultaneous steady-state demand is:

  • Per output: 1.5 A.
  • Four outputs together: 4 × 1.5 A = 6 A.
  • Power delivered to the coils: 24 V × 6 A = 144 W.

That 6 A excludes module electronics, sensors and other loads sharing the supply. It also excludes any additional pickup demand identified in the solenoid documentation.

Check the output's continuous inductive-load rating at the actual ambient temperature. Then check group limits, total module current, power connector contacts and every upstream distribution component. Four individually adequate channels can still overload a shared supply bank.

For example, two energized 1.5 A coils consume a 3 A group's entire continuous allowance. That leaves no allowance for additional loads or applicable derating. A nominally higher-current module may still have restrictive group assignments.

Do not assume an IO-Link communication port can directly switch a 1.5 A coil. Distinguish communication, sensor supply, auxiliary actuator supply and switched output capacity. A Class B port provides a separate auxiliary supply arrangement, not an automatic high-current output guarantee.

Check cable voltage drop at simultaneous load and verify the minimum voltage available at each energized coil. For daisy-chained power, the first cable and connectors carry downstream demand as well as local demand.

Confirm the required inductive suppression with both the output and solenoid documentation. Suppression affects switching stress and valve release time. Software staggering should not replace adequate hardware capacity unless the operating constraints are documented and reliably enforced.

Finally, define the required response to actuator power loss and communication failure. Keeping communication powered while removing actuator power does not, by itself, establish a compliant machine safety function.

Specify the installation, not just the I/O block

Your specification should identify the architecture, exposure limits and electrical capacity as separate requirements. Include the following information in the equipment schedule:

  • Environment: salt exposure, grease, chemical concentrations, cleaning temperatures and spray conditions.
  • Protection: required enclosure type or IP code, applicable test standard and any project-required third-party evaluation.
  • Materials: housing grade, gasket compatibility, connector materials and cable-jacket compatibility.
  • Connections: approved mating cordsets, unused-port caps, pin assignments, entry fittings and coupling instructions.
  • Loads: four 1.5 A solenoids, maximum simultaneous operation, sensor demand and documented pickup characteristics.
  • Power distribution: channel and group limits, module total, upstream protection, connector limits and voltage-drop calculation.
  • Maintenance: replacement access, cable identification, gasket inspection and checks after servicing.

For an enclosed arrangement, specify outside dimensions as height × width × depth, plus the required usable mounting space. Nominal inside shell dimensions are not the same as usable backplate area or component clearance.

For example, the 12 × 10 × 6 in 316L wall-mount enclosure measures 12 × 10 × 6 in outside (H × W × D). Those outside dimensions do not establish that your equipment fits. Confirm the mounting panel, terminal access, cable bends, door clearance and thermal calculation before selecting it.

The 316L stainless enclosure range provides material options for chloride exposure. Material selection still requires checking the actual cleaning chemistry and gasket compatibility.

Approve the final layout with every cutout located and every external fitting identified. Retain the enclosure until the exposed alternative meets the same documented environmental, electrical and maintenance requirements.

Enclosures in this article

EnclosureMaterialOutside H x W x D / displayRating
12 × 10 × 6 in316L stainless12 x 10 x 6 inRated NEMA 4X / IP66 by the manufacturer; not UL listed

Questions

Does an IP69K rating make exposed I/O suitable for salty, greasy washdown?

No. An ingress rating addresses specified water and dust tests, not universal chemical resistance. Confirm compatibility for the module housing, connector seals, port caps and cable jackets against the actual cleaner concentration, temperature and contact time. Also verify that the documented spray conditions cover the installation.

Can one machine mounted I/O module operate four 1.5 A solenoids?

Possibly, but check more than the individual channel rating. Four coils require 6 A simultaneously before other shared loads are added. Verify inductive-load capability, group limits, module total, auxiliary supply capacity, connectors, cable voltage drop and temperature derating. A communication port is not automatically an actuator output.

Does an IO-Link Class B port guarantee enough solenoid current?

No. A Class B port provides a separate auxiliary supply arrangement, but the device documentation determines the permitted current and function. Check whether the connected device switches the actuator, how its power is supplied, and which port, connector and module limits apply.

Should enclosed remote I/O use a 316L stainless enclosure?

Use 316L as a stronger starting point for chloride exposure, not as a guarantee against corrosion. Evaluate the actual chemicals, concentrations, temperatures and cleaning schedule. The door gasket, cable glands and other exposed fittings need their own compatibility checks, regardless of the enclosure's stainless grade.

Can a spray guard replace a higher washdown rating?

A suitable guard can reduce direct spray impact, but it does not change an equipment rating or establish chemical compatibility. Keep drainage, cleaning access and connector removal clear. Select the complete installation for the required exposure before treating a guard as additional protection.

Checklist before you order

Specify it once, built to your drawing

  • Environment and NEMA type: Type 1, Type 3R, Type 4, Type 4X, Type 6P, Type 12, Type 13 (manufacturer ratings, not UL listed)
  • Material: 304 stainless steel, 316L stainless steel, Powder-coated carbon steel, Aluminum, Polycarbonate, Fiberglass (FRP)
  • Size: inside or outside height, width and depth, with the depth your deepest component needs
  • Cutouts, glands and windows, dimensioned from one datum on each face
  • Mounting and access: wall, pole or stand, hinge side, mounting panel
  • Quantity: from one piece

Delivered in 10 business days, anywhere in the world. Counted from your order; for custom work, from your approval of the drawing.

Start from the washdown control panel buildRequest a custom quote

Washdown enclosures: sizes for this job

Keep reading

More on industries and applications

All articles

Buying guides

The guides behind this answer

All guides