Bottom conduit entry into a NEMA 4 floor-mounted enclosure

Mount the enclosure on a plinth, bring the conduits or glands through a drilled or gland-plate bottom, and seal each entry with a rated hub or gland. A rectangular cutout sealed to the pad with foam does not keep a Type 4 rating. Here is the sequence and what to put on the order.

NEMA4 Enclosure engineering team · Published October 28, 2026 · 6 min read

Conduits that turn up out of a concrete pad and enter a freestanding enclosure from below are normal practice, but they are the hardest entry to keep rated. The short answer: set the enclosure on a plinth, bring every conduit through a drilled bottom or a bolted gland plate, seal each one with a Type 4 conduit hub or cable gland, and never cut an open rectangle sealed to the pad. Everything below is the order of work that keeps the rating. Ratings named here are manufacturer ratings; our enclosures are rated by the manufacturer and are not UL listed.

What a Type 4 bottom has to do

A NEMA 4 enclosure is rated for hose-directed water from any direction, indoor or outdoor. That applies to the bottom face as much as the door. The rating lives in the gasketed joints and the sealed penetrations, not in the box itself. Every hole you add is a joint the manufacturer never made, so each one has to be restored with a rated device: a hub, a gland, or a bolted and gasketed plate.

This is also why a NEMA 3R enclosure is a different animal. Type 3R accepts rain and lets water drain, so an open bottom with drains is normal for it; see the rain-versus-hose comparison of NEMA 3R and NEMA 4 for why the two are not interchangeable. If the spec calls for Type 4 because of washdown or hose contact, a weeping bottom voids the point of the rating. The NEMA enclosure types guide lists what each type is built to resist.

Plinth first: get the bottom off the pad

A plinth is a base frame, usually 4 to 6 in (100 to 150 mm) tall, that the enclosure bolts onto and that bolts to the pad. You want one for three reasons: standing water on the pad never touches the enclosure's gasket line, you can reach the hubs underneath to tighten locknuts and check seals, and hose spray aimed low hits the plinth, not a rated face.

If no skirt kit exists for your box, have a plinth made: a welded stainless or galvanized channel frame sized to the enclosure footprint, with drilled anchor holes. Bed it on the pad with sealant, anchor it, then set the enclosure on a continuous compressible sealant bead and bolt through. The plinth becomes part of the unpenetrated wall, and the conduits pass through the cavity inside it.

Two rated ways through the bottom

There are exactly two ways to penetrate the bottom without giving up Type 4:

  • Drilled holes with Type 4 conduit hubs. One hole per conduit, sized to the hub thread. The hub's gasket and locking ring seal the hole; the conduit thread seals into the hub. Conduits that rise out of the pad and run straight to the enclosure are hub jobs.
  • A bolted gland plate. A plate, gasketed on its perimeter and bolted to a formed opening, carries the holes. You convert from conduit to cable in the pad or in a handhole and gland each cable. The gland plate article covers when a plate earns its keep on wall-mount boxes; the same logic applies under a floor-standing one, with the plate turned to face down.

Everything else — a rectangular cutout plugged with expanding foam, a bundle of conduits through one oversize hole — is a Type 3R habit. Foam seals against gas and vermin; it is not a hose-test joint. If water ingress or gas migration through the conduits themselves worries you, sealing conduits inside control cabinets compares the internal sealing methods that stop water traveling inside the conduit run.

How to do the installation

  1. Lay out the entries against the conduits as built. Conduits rarely come up where the drawing says. Measure each stub-up's center position and diameter relative to the pad, and transfer that to the enclosure bottom or gland plate with at least 1 in (25 mm) of metal between hole edges and 2 in (50 mm) to any wall or door frame flange.
  2. Decide hub or gland per entry. Conduit running to the box gets a Type 4 hub in the matching thread (usually 1/2 to 2 in NPT). Cable gets a gland; cable gland sizing and thread compatibility explains matching gland thread to plate thickness. Sealed multi-cable glands handle small groups of signal cables in one hole instead of swiss-cheesing the bottom.
  3. Cut the holes before the enclosure is set, if you can. A drilled hole is a clean, deburred, flat seating surface for the hub gasket; a hole cut under a live panel never is. If you order the enclosure from us, give us the layout and the holes arrive machined — the cutout designer lays out gland and hub holes on any face and checks spacing for you.
  4. Set and anchor the plinth. Level it in both directions, bed it in sealant, and torque the anchors. Conduit stubs should end 2 to 3 in (50 to 75 mm) above the plinth top so a hub or a coupling can be made up without lying on the concrete.
  5. Set the enclosure on the sealant bead and bolt it down. Do not bridge the plinth cavity yet; you need access from below for the next steps.
  6. Make up each hub or gland from below. Hole saw size per the hub instructions, deburr, gasket inside, locknut or clamping ring outside, and torque evenly. If you must field-drill, see how to cut a hole in a stainless enclosure for keeping a field cut sealed; the deburring and gasket-seating rules are the same on a bottom face.
  7. Seal the plinth cavity. With every entry made up, close the plinth ends. Fill the cavity around the conduits with foam or sealant only as vermin and gas blocking — the rating is already carried by the hubs and glands, so the foam is redundancy, not the seal.
  8. Label and photograph. A dated photo of the sealed underside is worth having at the next inspection, especially when the rating question comes up.

Checks when the job is done

  • Every penetration is a rated hub or gland with its gasket seated flat and its fastener torqued; no open knockouts, no half-engaged locknuts.
  • The gland plate (if used) is bolted at every hole with the perimeter gasket compressed evenly; check the corner bolts first, where plates leak.
  • A hose test on the accessible faces: spray the door, sides and plinth joint from a garden hose at close range for a few minutes, then open the door and look for tracks. Do not pressure-wash a gasketed joint you have not verified.
  • After the first rain or washdown, re-open and inspect. One wet underside tells you more than any document.

Mistakes that cost the rating

The big one is the rectangle-and-foam bottom. It reads as temporary even when it works, and it fails the definition of the rating even on a dry day. Close behind: self-tapping screws through the bottom flange, silicone smeared over an unrated hole, and hubs tightened with the enclosure already pinned to the pad so the locknut never fully seats. Field-cut holes with torn or dished edges do the same, because the hub gasket cannot bear on an uneven surface. And if the enclosure lives outdoors where the door will freeze shut or the interior will sweat at night, plan for that too — keeping electronics warm in an unheated outdoor enclosure covers heaters and insulation once the bottom is sealed.

What to put on the order

If the panel is being specified now, have the bottom entries made at the factory instead of cut in the field. Send a drawing callout with the bottom-face hole layout, or lay it out in the cutout designer and attach the export. Choose the material for the site — 304 stainless for indoor washdown, 316L where the pad sees salt or chlorides — from the custom enclosure options, and state the plinth. The enclosure is built to your layout from one piece and delivered in 10 business days from your approval of the drawing, with every hole machined and deburred, so the only work left on the pad is setting, bolting and making up the hubs.

A factory-cut bottom with a plinth and rated hubs is a permanent, inspectable installation. Foam under an open rectangle is not. Spend the extra day on the plinth and order the holes cut.

Questions

Can I cut a rectangular hole in the bottom and seal the enclosure to the pad?

No. A Type 4 enclosure has to resist hose-directed water on any mounted face, including the bottom. A field-cut opening sealed with foam or sealant to the concrete is not a rated joint: the gasket is the rated seal, and the pad is not part of it. That method is only seen on Type 3R gear, where the bottom is often open by design. For Type 4, every penetration goes through a drilled hole with a rated hub or gland, or a gasketed gland plate.

Does the enclosure have to sit on a plinth?

It is strongly recommended. A plinth of 4 in (100 mm) or more lifts the bottom face off standing water on the pad, gives room to make up hubs and glands underneath, and keeps the gasketed flange out of the splash zone. Bolt the plinth to the pad, set the enclosure on it, and seal the plinth-to-enclosure joint with a compressible sealant bead so it behaves like one body.

What is the difference between a conduit hub and a cable gland here?

A conduit hub is threaded onto rigid or IMC conduit and carries its own gasket and locknut, so the conduit itself stays part of the sealed wall. A cable gland seals around a cable instead of a conduit, and pairs naturally with a gland plate. Either maintains the entry seal; pick hubs when the conduit runs all the way to the enclosure, glands when you convert to cable at the pad.

How do I order an enclosure with the bottom entries already cut?

Specify the material, width, height and depth, then give the bottom-face layout: each hole position and diameter, or a gland plate with its knockouts. The cutout designer at /configure/ checks spacing and exports the layout, and the enclosure is delivered in 10 business days from your approval of the drawing with the cutouts already made, so no field cutting is needed.

Checklist before you order

Specify it once, built to your drawing

  • Environment and NEMA type: Type 1, Type 3R, Type 4, Type 4X, Type 6P, Type 12, Type 13 (manufacturer ratings, not UL listed)
  • Material: 304 stainless steel, 316L stainless steel, Powder-coated carbon steel, Aluminum, Polycarbonate, Fiberglass (FRP)
  • Size: inside or outside height, width and depth, with the depth your deepest component needs
  • Cutouts, glands and windows, dimensioned from one datum on each face
  • Mounting and access: wall, pole or stand, hinge side, mounting panel
  • Quantity: from one piece

Delivered in 10 business days, anywhere in the world. Counted from your order; for custom work, from your approval of the drawing.

Configure it in the builderRequest a custom quote

Keep reading

Related engineering answers

All articles

Buying guides

The guides behind this answer

All guides